An automobile detailing shop has the following jobs waiting to be processed. All jobs (cars requiring detailing) must first be cleaned, then waxed.
Job J1 J2 J3 J4 J5
Cleaning Time 7 2 5 10 8
Waxing Time 8 5 4 9 6
?b. What is the minimum makespan for this set of five jobs?