question archive The following Table 1 provides information for this question
Subject:Project ManagementPrice:3.86 Bought15
The following Table 1 provides information for this question.
Table 1 |
||||||
Activity |
Immediate Predecessor |
Time (day) |
ES |
EF |
LS |
LF |
A |
- |
2 |
|
|
|
|
B |
- |
6 |
|
|
|
|
C |
B |
3 |
|
|
|
|
D |
A |
7 |
|
|
|
|
E |
A |
3 |
|
|
|
|
F |
C, D |
2 |
|
|
|
|
G |
E |
3 |
|
|
|
|
H |
E, F |
5 |
|
|
|
|
I |
H, G |
4 |
|
|
|
|
a) Construct the network diagram for this project.
b) Complete ES, EF, LS, and LF
c) When is the latest start time for activity C and D?
d) What is the critical path?
e) What is the completion time for this project?
Purchased 15 times