Case Study #2 (Using Agile Approach – Relocation Project)
Project description: You are hired by the SCM Faculty Coordinator to move “stuff” of six SCM faculty from their old offices on the 3rd floor (Hyland Hall) to their new offices on the 4th floor (Hyland Hall).
Office |
Estimated number of boxes |
Preferred deadline - Handover of new office to the client |
#1 |
10 |
12:30 pm |
#2 |
10 |
1:30 pm |
#3 |
10 |
2:30 pm |
#4 |
5 |
11:00 am |
#5 |
5 |
10:00 am |
#6 |
5 |
9:00 am |
Tasks and estimated task times are as follows:
Packing and labeling boxes - 6 minutes per box
Loading boxes on dolly - 1 minute per box
Moving loaded dolly (1 trip) from 3rd floor to 4th floor - 25 minutes.
Unloading boxes into new offices - 1 minute per box
Moving empty dolly (1 trip) from 4th floor to 3rd floor - 15 minutes
Cleaning old offices – 10 minutes per office
Sprint meetings (face–to–face) – 15 minutes per meeting
Work package #1: Pack/label boxes in old office and load boxes on dolly.
Work package #2: Clean old office.
Work package #3 (in sequence): Move loaded dolly to new office, unload boxes in new office and return dolly to 3rd floor).
Story point for Work package #1:
Story point for Work package #2: 5 points per clean office
Story point for Work package #3: 4 points per box
NOTE: The following sources can provide definition and description of concepts/terminology used in Agile Approach:
Strategy #2
Sprint #1: 6:00 - 9:00
Sprint #2: 9:00 -12:00
Sprint #3: 12:00 - 3:00
Sprint #1 meeting: 6 – 6:15
Sprint #2 meeting: 9 – 9:15
Sprint #3 meeting: 12 – 12:15
#2) COMPLETE TABLES BELOW FOR STRATEGY #2. (12 points)
NOTE: Determine a Work sequence of Offices that will result in improved effectiveness and efficiency (compared to Strategy #1).
Person #1 – Work Sequence (Office #): TO BE DETERMINED BY YOUR GROUP
Person #2 – Work Sequence (Office #): TO BE DETERMINED BY YOUR GROUP
Person #1 Schedule:
Work package #1 Start time |
Work package #1 Finish time |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Person #1 Schedule:
Office # |
Work package #2 Start time |
Work package #2 Finish time |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Person #1 Schedule:
Office # |
Work package #3 Start time |
Work package #3 Finish time |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Person #2 Schedule:
Office # |
Work package #1 Start time |
Work package #1 Finish time |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Person #2 Schedule:
Office # |
Work package #2 Start time |
Work package #2 Finish time |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Person #2 Schedule:
Office # |
Work package #3 Start time |
Work package #3 Finish time |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Completion (DONE) statistics: (Effectiveness)
Office # |
Preferred deadline - Handover of new office to the client |
Office “DONE” time |
Delay in handover of new office (hours: minutes) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Labor statistics (Efficiency)
Worker |
Time Worked |
Idle Time |
Total time |
Utilization (percent)
|
Person #1 |
|
|
|
|
Person #2 |
|
|
|
|
Purchased 7 times